Case Study
Ascot Racecourse
Flat & Pitched Roof Refurbishment with M&E Enclosure rebuild
Stadium Support Services was appointed by Ascot Racecourse to carry out a full refurbishment of the Pavilion roof. This followed a detailed condition survey which identified urgent works to both the flat and slate-pitched roofs, alongside the removal and replacement of plant housing and walkways.
The Challenge
The project took place in a live venue with tight weather windows and active event scheduling. Key challenges included shutting pedestrian areas, removing plant equipment and housing, and lifting materials by crane. All roofing works were weather-dependent, requiring flexible planning and close coordination with the venue team.
Scope of Work
-
Decommissioning of plant disconnection and removal of M&E
-
Flat roof replacement removal of grating and walkway, installation of new Renolit roof
-
Pitched roof replacement strip existing slate, install Canadian Glendine slate
-
M&E plant enclosure fabricate and install rolled steel and box profile sheeting
-
Crane lifting services full lift management for plant and materials
-
Reconnection of plant and handover to client
The Solution
Our team planned works around events and weather, maintaining constant site communication. Crane lifts, roofing and M&E works were safely coordinated, and each phase was delivered without disruption. The project was completed on time, on budget and to a high standard.
“This was a complex project with several moving parts, and the Stadium Support Services team managed it very well from start to finish. Their planning, communication, and on-site coordination were solid throughout, particularly given the challenges of working around events and the weather. They kept us informed at each stage and completed the project on time and to a high standard. We’re very pleased with the end result.”

300sqm
Pitched Roof

50sqm
Flat Roof

50+
Crane Lifts