Case Study

Coventry Building Society Arena

Structural Coatings & Superstructure Cleaning

Stadium Support Services delivered two specialist access projects at the CBS Arena in Coventry. The first involved the application of protective coatings to internal and external structural steelwork, while the second focused on cleaning the arena’s external cantilevered superstructure.

The Challenge

The CBS Arena features hard-to-reach areas, both internally and externally. Our team had to couple rope access and MEWP expertise with specialist ICATS-accredited painters to carry out structural coatings. Live events, high footfall areas and tight scheduling added complexity, requiring a responsive approach. High-level cleaning of the external superstructure presented further challenges, needing a safe blend of rope access and a 57m MEWP while maintaining operations at ground level.

Scope of Work
  • Surface preparation ST3 standard via pneumatic and rotary tools
  • Internal coatings undercroft steel across 7 sections
  • External coatings superstructure areas, cleaned and repainted
  • Coating system approved primer, intermediate and topcoat system
  • MEWP deployment 57m boom used for high-level works
  • Water-fed cleaning ground-fed supply to rope access and MEWP teams
  • Coordination works timed around public use and stadium operations
  • Access strategy rope access, PASMA towers and fall arrest systems

 The Solution

Our multi-access teams used a combination of rope access, MEWPs, PASMA towers and temporary fall arrest systems to safely reach all areas of the internal undercroft and external superstructure. Steelwork was prepared to ST3 standard, feathered back and fully recoated using an approved three-part protective system. Cleaning teams used abrasive brushes and ground-fed water lines to deep clean high-level steelwork with minimal disruption. Thanks to strong planning and a flexible on-site presence, both projects were completed safely and within the required timeframe.
“The team at Stadium Support Services did a great job on the CBS Arena. Their knowledge and experience of specialist access meant there was minimal disruption to our operations. The entire process was handled safely and efficiently. We were impressed with their attention to detail and the professionalism of their technicians.”
Alan Pickering, Head of Facilities, CBS Arena

Hours

2,800sqm
steel painted

Hours

10 weeks
 to completion

SQM

60m
working at height