Case Study

QPR FC, Loftus Road Stadium 

Asbestos Cement Roof Replacement & New Metal Profile Roofing Installation

As Official Facilities Management Partner to Queens Park Rangers FC, Stadium Support Services removed the asbestos cement roof above the Stanley Bowles Stand at Loftus Road Stadium and installed a new metal profile roofing system.

The project was completed within a live stadium environment over a tight 20-day programme. Careful planning, stringent safety controls and close coordination with the club ensured the works were delivered ahead of the scheduled pitch renovation.

The Challenge

Scope of Work

  • Construction of a scaffold loading bay providing roof-level access, as well as safe loading and unloading of roofing materials
  • Removal of the existing roof and safe disposal of hazardous asbestos waste
  • Air monitoring, waste management and PPE controls throughout the asbestos removal process
  • Installation of trackway to mitigate damage to the playing surface
  • Installation of safety netting and debris netting using MEWPs
  • Installation of guardrails to the front and rear roof edges
  • Supply and installation of a new roof consisting of box-profiled steel sheeting

The Solution

Client Testimonial

“As Official Facilities Management Partner to QPR FC, Stadium Support Services plays a key role in maintaining and improving our facilities. This project showcased the team’s ability to deliver complex works safely within a live stadium environment and to a demanding programme. The works were completed on time and to a high standard, providing us with a long-term roofing solution for years to come.”

Darren Batthews, Head of Operations, Queens Park Rangers FC

Get in Touch

Delivering projects, reactive maintenance and FM solutions for the Sport, Leisure and Commercial Property sectors.

Email: info@StadiumSupportServices.co.uk
Website: www.StadiumSupportServices.co.uk
Telephone: 020 8898 7253

Hours

20 days
to complete project

Liquid

35 Tonnes
of asbestos cement removed

Liquid

2000 SQM
roofing sheets removed and installed

Hours

10,000+
fixings removed and replaced