Case Study

Grosvenor Gardens, London

Heritage Chimney Remediation via Rope Access

Stadium Support Services delivered specialist rope access remediation works to a heritage residential property at Grosvenor Gardens in central London.

The project focused on the repair and reinstatement of four high-level chimney breasts, including stone conservation works, flue reconstruction and the installation of terracotta chimney pots, all completed in line with the architect’s detailed specification.

The Challenge

Scope of Work

  • Design and implementation of a safe work at height access system
  • Installation of terracotta chimney pots and cowl caps
  • Breaking out and repointing lime mortar joints
  • Fixing and securing Portland stone decorative features
  • Conservation-grade steam cleaning of stonework
  • Installation of bespoke Portland stone elements in accordance with heritage conservation requirements and approvals

The Solution

Client Testimonial

“The team at Stadium Support Services did a great job on the CBS Arena. Their knowledge and experience of specialist access meant there was minimal disruption to our operations. The entire process was handled safely and efficiently. We were impressed with their attention to detail and the professionalism of their technicians.”

Alan Pickering, Head of Facilities, CBS Arena

SQM

56
terracotta cowl caps installed

Hours

4
rope access operatives

Hands shaking

75kg
of lime mortar used

Hours

5-week
programme duration