Case Study

Southern Water

Burham Water Treatment Centre Welfare Area Development

In partnership with Equans FM and their client Southern Water, Stadium Support Services were commissioned to develop and upgrade the staff welfare facilities at the Burham Water Treatment Centre.

As part of their commitment to the welfare of their workforce, Southern Water made a significant and widescale investment to develop and upgrade the welfare facilities across their sites.

Led by Equans, the project is set to be rolled out nationwide with Stadium Support Services as a lead delivery partner.

Challenge

With a short operational window to access and complete the works, the Stadium Support Services team only had 10 days to fully complete the works.

With multiple challenges surrounding old pipework that was no longer fit for purpose, a brand new water system was required to ensure latest regulations were adhered to. The pipework would accommodate a mains-fed shower system, new kitchen appliances, and the installation of water-saving devices across all areas.

Solution

Plans were mutually agreed with the onsite client, with all critical components plotted within a GANTT chart to ensure timely delivery. Existing infrastructure was removed, with a large team deployed each day for 10 days to ensure the build was completed to time, and to plan.

Burham Kitchen Area

New kitchen and integrated appliances, installing the latest energy efficient appliances, instant hot water tap and water-saving devices.

Burham Bathroom Area

Bathroom area with brand new appliances with water-saving devices, including washing machines.

Result

Within the Burham site, the main staff areas were upgraded to meet the specific needs of the users within today’s operational capacity.

Split into two sections, the areas house a new open-plan kitchen, a contemporary bathroom, and the installation of new toilets. Completed within the planned time frame to a very high standard, resulting in a very happy workforce and satisfied clients.

“It was a pleasure to work with Stadium Support Services on this project. Professional, understanding, quick and efficient, Stadium Support Services went above and beyond to make the project a huge success for our client, Southern Water.

Patrick Fisher

Senior Project Manager, Equans

With a short operational window to access and complete the works, the Stadium Support Services team only had 10 days to fully complete the works.

2,000 litres of water saved

50m2 Area developed

50+ Litres of paint used

10 Days to completion

Subscribe To Our Newsletter

Subscribe to see the latest news and quarterly updates from Stadium Support Services!

You have Successfully Subscribed!